Published on Mon., January 12, 2015
The Top 5 ongoing activities for the new Heritage High School include:
- Heavy earth moving at the new bus turn around loop
- Pouring concrete slabs
- Steel erection
- Masonry wall erection
- Installation of under slab utilities
Fun statistics include:
- We have installed 554 tons of steel to date
- We have worked just over 70,000 man hours to date
- There will be 400,000 bricks in the skin of the building
- There are 480,000 concrete masonry blocks in the structure
- There will be 20,000 bags of mortar used on the building
- There will be 1,800 yards of grout fill in CMU block walls